Understanding the Rooftop Solar Timeline in Maharashtra
From the day you submit your online registration to the day the central subsidy hits your bank account, the entire process takes approximately **45 to 60 days**. Knowing the milestones and active SLAs helps you coordinate with your vendor.
Rooftop Solar Milestones (45-60 Days Process)
| Phase / Step | Activity Details | Average Duration |
|---|---|---|
| Day 1 - 7 | Submit online application on the National Portal; MSEDCL inspects transformer capacity. | 7 Days |
| Day 8 - 10 | Feasibility approval issued. Contract signing with empanelled vendor. | 3 Days |
| Day 11 - 25 | Material procurement (panels, inverters, structures). Site prep & physical installation. | 15 Days |
| Day 26 - 32 | Vendor submits Work Completion Report. Online request for net meter testing. | 7 Days |
| Day 33 - 42 | Joint physical inspection by MSEDCL. Net meter installation and plant commissioning. | 10 Days |
| Day 43 - 60 | Submit bank details on portal. MNRE reviews documentation & releases subsidy via DBT. | 18 Days |
Standard Operating SLAs for MSEDCL
Under the Maharashtra Right to Services Act, MSEDCL has binding SLAs for solar integration:
- Technical Feasibility Review: 15 working days from submission.
- Joint Inspection and Meter Setup: 10 working days from Work Completion upload.
- Commissioning Certificate Issuance: 3 working days from physical testing.