Uttar Pradesh Application Timeline Guide (2026)

📅 Fact-Checked: June 25, 2026⏱️ 10 min read
Rahul Sharma
Written by Rahul Sharma, B.Tech Electrical
✓ Verified ExpertLast Reviewed: June 25, 2026Next Review: Sept 2026

Rooftop Solar Installation Timeline in Uttar Pradesh

The entire process from submitting your online registration to receiving your stacked subsidies takes approximately **45 to 60 days**. Understanding the milestones helps you monitor your installation progress.

UP Solar Milestones (45-60 Days Process)

Phase / Step Activity Details Average Duration
Day 1 - 8 Submit application on the portal; UPPCL inspects local transformer capacity. 8 Days
Day 9 - 12 Feasibility approval issued. Sign contract with empanelled vendor. 4 Days
Day 13 - 27 Material procurement and installation. Solar array structures mounted. 15 Days
Day 28 - 35 Vendor submits Work Completion Report. Request bi-directional meter testing. 7 Days
Day 36 - 45 Physical inspection by UPPCL. Net meter installation and plant commissioning. 10 Days
Day 46 - 60 Submit bank details. MNRE & UPNEDA process and release stacked subsidies via DBT. 15 Days

UPNEDA & UPPCL Service Level Agreements (SLAs)

UPERC mandates clear timelines for rooftop solar integrations:

  • Feasibility Review: Must be completed within 15 working days from submission.
  • Net Meter testing and installation: Within 15 working days from work completion report submission.