Home » Delhi Rooftop Solar » Common Problems

Delhi Common Problems Guide (2026)

📅 Fact-Checked: June 25, 2026⏱️ 10 min read
Rahul Sharma
Written by Rahul Sharma, B.Tech Electrical
✓ Verified ExpertLast Reviewed: June 25, 2026Next Review: Sept 2026

Troubleshooting Solar Delays in Delhi

If your application with BSES or TPDDL stalls, here are the standard resolutions to common problems:

1. Sanctioned Load Mismatch

Problem: Your vendor proposes a 5kW system, but your CA number only has a 3kW sanctioned load. Application rejected.
Solution: Apply for load enhancement via the BSES/TPDDL portal. You must pay the SLD (Security Deposit) for the extra load before re-applying for solar feasibility.

2. RWA/Society NOC Rejection

Problem: The DISCOM inspector notes that you live in a multi-story building and demands a roof rights NOC.
Solution: Obtain a signed letter from the society president confirming you have exclusive rights to the specific roof patch where panels are installed.

3. Net Meter Unavailability

Problem: System is installed, but the DISCOM states they are out of net meters.
Solution: DERC rules permit consumers to procure their own net meters from approved vendors. Purchase an L&T or Secure meter, get it tested at a NABL lab, and provide the test report to the DISCOM engineer to expedite commissioning.

4. GBI Not Reflecting in Bill

Problem: It has been 3 months since commissioning, but GBI credits aren't showing up.
Solution: Ensure your solar generation meter (a secondary meter installed by the DISCOM to track total solar output) is communicating properly with the grid. File a ticket on the DISCOM app for a meter reading check.

Your Solar Journey Continues

Keep reading the Delhi cluster to ensure a successful rooftop installation:

← Previous: Application TimelineNext Step: Electricity Tariffs →