Delhi Rooftop Solar Timeline (2026)

The workflow with BSES and Tata Power is heavily digitized. A standard residential installation from registration to subsidy payout takes about **45 to 60 days**.

The 60-Day Roadmap

Phase Action Timeline
1. Feasibility Application Apply on National Portal. DISCOM verifies transformer load. 7 Days
2. Execution Vendor procures DCR panels, installs structure, and wires the system. 15-20 Days
3. Work Completion Vendor uploads CEIG/safety certificates and WCR to the portal. 3-5 Days
4. Inspection & Metering DISCOM engineer visits. Net meter is tested and installed. Commissioning generated. 10-15 Days
5. Subsidy Processing Submit bank details. MNRE validates and transfers the DBT subsidy. 15-20 Days

Note: The Generation-Based Incentive (GBI) will automatically start reflecting as credits on your regular monthly electricity bill within 1-2 billing cycles after commissioning.